Dedicated drives prolong life of cranes

Request your FREE weekly copy of the Manufacturingtalk email newsletter. News about Drives, motors and power transmission, couplings, clutches and more every issue. Click here for details.

ABB drives have helped an aluminium producer prolong the life of its cranes by up to 10 years by installing drives featuring a software macro dedicated to crane control

ABB drives have helped an aluminium producer prolong the life of its cranes by up to 10 years Anglesey Aluminium, based at Holyhead on Anglesey, Wales, uses 4, 30 tonne cranes to load its smelting pots with alumina

The nature of the aluminium smelting process means the company cannot stop production, so the cranes are in constant use and have not had a major overhaul since they were installed in 1970.

It was becoming difficult to get spare parts for the control system and the heat from the smelting pots had also caused the power cables to become brittle.

Anglesey Aluminium's Electrical Engineer, Des Frost, says: "We clearly needed to do something to improve the condition of the cranes and make them easier to operate and maintain.

We examined the cranes and found that they were mechanically sound - all that was needed was to refurbish the electrics.

As we already had variable speed on the cranes, achieved using thyristors, we decided to go for a variable speed drives system.

We had used ABB drives on a conveyor application and to move our unloading machines at our jetty.

These drives had given good performance and this decided us in favour of ABB.

The drives themselves are easy to use and the programme is accessible to make changes to the starting speed and acceleration." The ABB ACS 600 Crane Drive was chosen for the application.

The drive is designed for crane operations of all types and includes a software macro dedicated to crane control.

Frost decided to source the drives through Central Electrical, because of their alliance agreement with ABB, which provides quick response when needed.

Installation and commissioning of the drives was critical.

Because of the nature of the aluminium smelting process, the cranes could only be worked on for 12 hours at a time.

At the end of this time, the crane had to be back in full working order to continue keeping the pots supplied with alumina.

The main contract was awarded to Professional Lifting Services (PLS) of Sheffield who made up the panels and did as much preparation work as possible before the installation, in order to cut down on the crane downtime.

ABB along with PLS and Frost pre-commissioned the drives before they were installed.

Frost continues: "ABB and Central Electrical staff were on site during the most critical phase of removing the old panels and installing the new drive panels.

This had to go smoothly as the crane had to be in working order again at the end of the planned 12 hours downtime stage." The cranes environment also causes difficulties.

The smelting pots sit on an unearthed platform, with large open DC busbars carrying 165 kA.

This produces massive magnetic fields that magnetise tools and equipment, prevents the operation of electric drills, and interferes with welding.

The drives themselves did not need shielding against the magnetic fields, as they are situated on the cranes 10 metres above the busbars, but heat is a problem.

The drives need to operate in a summer ambient temperature of up to 48 degrees centigrade and were oversized to account for this.

Frost also specified a temperature monitoring system for the drives, which switches on an air conditioning unit to feed the panels when the temperature becomes critical.

The drive panels are to IP 54 to protect the drives against the ingress of dust.

"Overall I am very pleased with the way the project has gone, and with how ABB, Central Electrical and PLS have worked with us to complete this job," says Frost.

"We have refurbished two cranes so far, and will do another two soon.".

ABB Automation Tech (Drives and Motors): contact details and other news
Email this article to a colleague
Register for the free Manufacturingtalk email newsletter
Manufacturingtalk Home Page

Search the Pro-Talk network of sites

Visit the Parker Hannifin Electromechanical Automation web site