Airflow simulation protects stored
medicines
Airflow evaluation software helps HVAC system meet pharmaceutical company's requirements for storing medicines
Flomerics' consultants used their Flovent software to evaluate design alternatives which helped Eichleay Engineers of California design an air handling system that keeps temperatures in a pharmaceutical warehouse within +/- 1F Flomerics' consultants evaluated design alternatives and identified a fan configuration that met the pharmaceutical company's requirements for both temperature variation and air velocity
This article was originally published on Manufacturingtalk on 2 Aug 2007 at 8.00am (UK)
Related stories
Simulation reduces RFID label development time
By simulating radio frequency identification labels with electromagnetic simulation software a company has reduced the time to develop RFID labels from 7-10 days to 2-3 days.
Flotherm thermal analysis software
New response surface optimisation enables engineers to visualize the complete interaction of the parameters with the design goal
"The HVAC system has been in operation for over a year and the temperatures in the warehouse have never been outside the customer's specified range," said Michael Simpson, Mechanical Engineer for Eichleay Engineers.
A pharmaceutical warehouse contains 49,200 square feet of warehouse storage space and has a roof height that varies from 25 to 28 feet.
In order to maximise the life of the product stored in the facility the client established a requirement that the temperature throughout the entire interior space be held between 67F and 74F and at less than 50% relative humidity.
"We began the project by using standard computer calculations to design an HVAC system that was capable of keeping the temperature in the building at the required level," Simpson said.
"This system could get us to the right average temperature but left us with very little safety margin".
"We called the two leading software companies in the HVAC CFD industry.
We knew that they both offered people with extensive experience in air flow simulation modeling.
One of the companies told us that we would have to wait several weeks before they could even take a look at our problem.
On the other hand, Flomerics told us they would be there the next day to give us an estimate and get started on our project".
Flomerics' consultant Chris Wark simulated the existing building and several alternatives using different types of fans.
He found that the addition of 50 Airius destratification fans reduced the temperature variation within the building to a +/- 1F level.
The building's HVAC control system was designed to issue an alert to plant operating personnel whenever temperatures in the space fall outside a +/- 3.5F limit from setpoint.
"The new HVAC system has been up and running for about 18 months and since then, the temperature alarms have not shown any excursions," Simpson said.
Most importantly, the customer is extremely pleased that the building has met their requirements". Request a free brochure from Flomerics ...