Product category:
Automatic and robotic welding systems
News Release from: Motoman Robotics (UK) | Subject: Robotic arc welding cells
Edited by the Manufacturingtalk Editorial
Team on 04 September 2003
Robotic arc welding cells installed
quickly
When an automotive subcontractor wanted to expand parts fabrication quickly, robotic welding cells were installed and up and working in a short time, thanks to their 'single-lift' design.
When an automotive subcontractor wanted to expand parts fabrication quickly, robotic welding cells were installed and up and working in a short time, thanks to their 'single-lift' design Cowley-based UYS, a first-tier subcontractor owned jointly by Yutaka Giken and Honda of the UK Manufacturing, has supplied the latter with welded sub-assemblies for the Accord and Civic since 1998
This article was originally published on Manufacturingtalk on 14 Jul 2000 at 8.00am (UK)
Related stories
Ford uses Motoman robots for sealant application
As an alternative to fitting conventional gaskets to seal the mating faces of vehicle engines, Ford finds that a quicker and more economical method is to lay down a bead of sealant by robot.
Articulated-arm robots offer larger envelope
The SK Series of articulated-arm robots from Motoman has been replaced by a new range, designated UP Series.
When in 2000 the subcontractor was looking to support the manufacture of the Honda CRV, which went into mass production in November 2001, it chose Motoman to supply the robot welding cells owing in part to the speed with which they could be installed.
Said Mike Logue, engineering and sales manager at UYS, "Once the decision had been made that we would support CRV production, speed was of the essence to get the welding cells in and producing parts.
We needed to meet an initial supply date of August 2001 and ramp up to mass production from the October.
Further reading
Robots weld X400 seat frames
Two robotic welding cells have been supplied by Motoman to the Birmingham factory of Lander Automotive to automate the manufacture of complex assemblies for the new Jaguar X400 saloon car.
Robots polish off catrering ware much quicker
One of Europe's leading stainless steel catering and sanitary ware equipment manufacturers, W and G Sissons, has embarked on a far-reaching programme to automate polishing at its Chesterfield factory.
Motoman appoints systems integrator in Essex
Specialist motion control system builder, Micromech, based in Braintree, Essex, has been appointed a systems integrator by articulated-arm robot supplier, Motoman Robotics (UK), Banbury.
We placed the order in April that year and were quoted by Motoman a 12-week lead-time for the delivery of 11 cells, later to be increased to 13.
"So all the robotic arc welding equipment for the CRV was able to be installed during our summer shutdown.
Some cells were in and running before that, as I and some of my colleagues were using them to fine tune the production of a few difficult welded assemblies during the holiday." Key to the ability of Motoman to supply its ArcSystem cells so quickly is the single-lift design.
The pallet-mounted unit is loaded onto a lorry as a complete system, with guarding and full CE marking.
When each cell arrived, it could be off-loaded quickly and the services connected.
As Motoman had already written most of the programs as part of the contract, the cells were ready for start-up the same day.
Logue commented that other robot suppliers including the incumbent, which also quoted for the new contract, offered to deliver their equipment and build the guarding on site, which would have taken two weeks per cell.
Moreover, the lead-time for delivery was two months longer than Motoman's, whose price turned out to be between five and 10 per cent less than the competition.
Overall, the project took five months from inception to completion, twice as fast as the original start-up for the Accord in 1998/99.
The first-tier assemblies supplied by UYS to Honda for the CRV are predominantly exhausts, but include suspension components and stiffening rods, splash guards and side-impact bars.
It was the addition of other welded assembles such as the steering hanger, and a late design change to a suspension arm, that resulted in the original Motoman order being nearly doubled to 25 welding cells.
Two further cells were delivered at the end of May 2003 for producing suspension arms from galvanised steel for the 2004 Civic model.
The number of car sets produced by the Motoman equipment totals 550 per day over two shifts.
Most cells are single-robot, twin-station and all include the latest Motoman UP-Series, 6-axis articulated-arm robot which has all services routed inside the frame, avoiding trailing cables and hoses.
A few single-station cells are reserved for MIG welding more complex parts such as the exhaust manifold, as production cycle time is long compared with the fixturing time.
Only one Motoman cell performs spot welding.
Equipment up-time is paramount in a mass production environment such as this.
Concluded Logue, "Motoman robots are inherently reliable and are designed so that our operators can easily recover most day-to-day faults, which means that prolonged downtime is rare.
We have had good support from Motoman's Banbury centre and from their head office in Sweden.".
• Motoman Robotics (UK): contact details and other news
• Email this article to a colleague
• Register for the free Manufacturingtalk email newsletter
• Manufacturingtalk Home Page

